April 27, 2025The Suva City Council is ready to herald a new era of safety and convenience for public transport users in Suva as the extensive rehabilitation works at the Suva Bus Stand approach completion.
This vital infrastructure upgrade began in February 2025 in collaboration with the Fiji Roads Authority. The process underwent a meticulous planning and operational stage with its key priority to minimize disruptions for bus operators and commuters traveling to and from the city. Despite a few unforeseen setbacks encountered, the project has steadfastly progressed through its carefully defined stages, each contributing significantly to the overarching objective of a vastly improved public transport hub.
Suva City Council Acting CEO, Mr. Tevita Boseiwaqa said the Council is optimistic about the execution of the project given the steady progress achieved across all stages.
“As the Fiji Roads Authority diligently focuses on the final touches, the Council eagerly looks forward to fully opening the revitalized Suva Bus Stand to the general public. The long-standing issues of poor drainage and hazardous road conditions that commuters had to endure will now be a thing of the past. The imminent completion of this project underscores the Council’s steadfast commitment to providing a safer and ultimately more user-friendly experience for each and every commuter.”
Mr. Boseiwaqa further elaborated on the collaborative effort: “The seamless partnership with the Fiji Roads Authority has been instrumental in reaching this point. Their expertise and dedication have been invaluable in navigating the complexities of this large-scale undertaking. From the initial planning stages to the intricate execution of each phase, their technical knowledge and collaborative spirit have been crucial to the progress we’ve achieved.”
Key progress updates as of today include:
Stage 1: Entire Bus Stand and Connecting Road – Underground Drainage Upgrade: 100% COMPLETE
Stage 2: Road and Pavement Upgrades:
- Phase 1 (Rodwell Rd Bus Stand Entry, inner lane): Milling, Excavation, Basecourse, Cement Stabilization, Basecourse Curing, Asphalt Pavement and Surface Drainage are complete. Linemarking is pending.
- Phase 2 (along Western Bus Stand & Escott St): Milling, Basecourse, Cement Stabilization, Basecourse Curing, Asphalt Pavement and Surface Drainage are complete. Linemarking is currently at 20%.
- Phase 3 (tarmac between Terminal 2 & 3): Surface Prep, Asphalt Regrading, Basecourse and Asphalt Pavement are complete. Surface Drainage is at 60% and linemarking is pending.
- Phase 4 (tarmac between Terminal 1 & 2): Surface Prep, Asphalt Regrading & Pavement, and Hump construction are complete. Surface Drainage is at 85% and linemarking is pending.
The Council understands the disruptions caused by such a significant undertaking and would like to thank the public for their patience and cooperation throughout these essential works. The work is set to be fully completed in the coming weeks. Looking ahead, the Suva City Council is also actively planning future projects aimed at further enhancing the city’s infrastructure and public spaces.